Childhaven
Project:
- 53,700 ft2 Four-story Facility Plus Underground Parking Garage
Team:
- Owner - Childhaven
- Architect - Miller/Hull Partnership
- GC - GLY Construction
- HVAC - PSF Mechanical, Inc.
- Electrical - Johnson Electric
- Fire Protection - Patriot Fire Protection
HVAC Systems:
- Two packaged York rooftop VAV variable air volume units with gas heat
- Fan powered terminal units with electric heat
- Type I and Type II kitchen exhaust hoods
- Server room split system
- Packaged heat pumps serving elevator machine rooms
- Elevator pressurization fans
- Garage exhaust system
- Alerton EMCS system
Energy Saving Strategies:
- EMCS optimal start scheduling of HVAC equipment
- High-efficiency HVAC equipment with gas heat
- ECM motors on terminal units
- Economizer control of rooftop units to provide “free” cooling with outside air
- VFDs on rooftop unit supply fans
System Benefits/Goals:
The Childhaven facility was constructed under the design/build concept which proved very beneficial to the owner by delivering a complex mixed-occupancy structure under a tight schedule. Severe space constraints due to height limits proved a challenge to the mechanical designer/installers. Special consideration was given to sound control which produced a quiet building both internally, and due to code restrictions, externally.