Puget Sound Blood Center Phase II
Project:
-
60,000 ft2 Laboratory & Office Space
- Existing Warehouse Conversion to Laboratory & Office
Site Location:
- Renton, WA
Team:
-
Owner - Puget Sound Blood Center
-
Architect - Mithun
-
Engineer - SIDER + BEYERS Associates, Inc.
-
GC - BNBuilders, Inc.
-
HVAC - PSF Mechanical, Inc.
HVAC Systems:
-
Chilled water using rooftop air-cooled scroll compressor chillers (N+1 redundancy), 240 tons total
-
Indoor custom air handler, 68,000 CFM VAV with air-side economizer
-
Specialty exhaust systems
-
DDC EMCS
-
Full build-out of existing warehouse shell
- Specialty exhaust systems
Unique Design Challenges:
-
Ultra fast track project schedule/coordination
-
Extreme logistical challenges:
- Quick cycle equipment procurement
- Construction initiated prior to design completion
- GC initiated structural solution to mechanical/electrical support requirements (interstitial structural steel support grid beneath 30’ roof)
-
PSF engaged as coordination control point for GC, initiated BIM process
- Overlapping construction/design process - PSF utilized temporary supports to allow pre-installation of major duct runs and mechanical components while interstitial structure was designed, procured and erected
Energy Saving Strategies:
- Air-side economizers
-
VAV air distribution throughout office and laboratory areas
-
DDC EMCS controls
-
Variable frequency drives
-
Variable flow primary chilled water system
- Plug supply and relief fans