Quadrant East Campus Corporate Park Parcel 3-B
Project:
-
72,000 ft2 3-story Building
Site Location:
-
Federal Way, WA
Team:
-
Owner - Quadrant Corporation
-
Architect - Lance Mueller and Associates
-
GC - GLY Construction Co.
-
HVAC - PSF Mechanical, Inc.
-
Electrical - Johnson Electric
-
Fire Protection - Patriot Fire Protection
HVAC Systems:
-
Standard temperature variable air volume
-
Series fan induction terminal with VAV and electric heat
-
Series type variable air volume valves for cooling
-
Central toilet exhaust system utilizing a rooftop fan
-
Raised curb sound attenuating system for roof units
-
100% airside economizers
-
Farr 30% pleated filters
Energy Saving Strategies:
-
Efficient scroll compressors
-
Premium efficiency supply and relief fan motors
-
VAV supply and relief fans for the Trane Intellipak units result in both energy savings and accurate control of duct and building static pressure
- Gas heating is used for nighttime heating and morning warm-up, reducing the use of electric energy